In December 2021, Mayor Bowser and DDOT told project staff to go ahead with Concept C. That plan would have removed the reversible lanes and added one-way protected bike lanes on both sides of Connecticut Avenue. It also called for new turn lanes, pedestrian refuge islands, curb extensions and a ban on right turns on red. The plan DDOT now has scheduled for the Chevy Chase blocks in 2026–2027 is much smaller. It is a list of single corners: a new crosswalk at Oliver Street, a banned left turn at Northampton Street, a bus stop moving across Military Road, and a pedestrian signal at Legation Street that is installed and waiting on Pepco.
If you drive, walk or take the bus on upper Connecticut Avenue, the order of the work matters more than the list itself. The early changes are small: a few feet of curb, two parking spaces, one turn you can no longer make. The changes that alter how cars move through the neighborhood, at Harrison Street, Jocelyn Street and Nebraska Avenue, are in a second phase that DDOT expects to build in 2027–2028.
How a Corridor Plan Became a List of Corners
The project began in December 2019 as the Connecticut Avenue NW Reversible Lane Safety and Operations Study. DDOT turned off the rush-hour reversible lanes on March 19, 2020. It removed their signs and markings in summer 2022, and lowered the speed limit from 30 to 25 mph that same summer. In early 2023, DDOT leadership asked staff to take a fresh look at every concept, Concept C included, after a large number of comments about the parking that Concept C would have removed.
In April 2024, then-acting DDOT director Sharon Kershbaum told a Council hearing that the redesign would not include bike lanes. WTOP reported her words: "It has always been a safety project. It's on our 'High Injury Network.' And somehow, over the years, that kind of morphed into a bike project."
After that, the work narrowed to intersections. DDOT showed ANC 3/4G its intersection proposals on June 23, 2025, as part of a 22-intersection package for the whole corridor. In December 2025 it dropped the hardened centerlines from the plans, saying their maintenance needs outweighed their safety benefits. The formal notice to ANC 3/4G is dated March 20, 2026, and its comment period closed May 4. On the DDOT project site, implementation began in summer 2026, each intersection is built separately, and the agency expects to finish within about two years.
The First Phase on the Chevy Chase Blocks
DDOT scheduled the Chevy Chase share of Phase 1 for 2026–2027. North to south, it looks like this.
At Oliver Street, near the top of the project area, DDOT will add a crosswalk across Connecticut Avenue on the south leg of the intersection. Oliver is still listed in design. Of the Chevy Chase intersections, it is the only one in the first phase that has not reached the pre-construction stage.
Northampton Street gets the most noticeable change for drivers in this phase. Drivers heading south on Connecticut Avenue will no longer be allowed to turn left onto eastbound Northampton. Stop bars will move to improve sight lines. DDOT will also remove exactly two off-peak parking spaces on Connecticut Avenue, one on the west side of the intersection and one at the southeast corner, for better visibility.
At Military Road, the northbound bus stop moves to the north side of the intersection. That takes away some off-peak parking where the new stop goes, and the old stop location becomes off-peak parking again. Morrison Street and Kanawha Street get improved signage for pedestrian safety.
On DDOT's status table, Northampton, Morrison, Military, Kanawha and Ingomar are all in pre-construction. DDOT defines that as plans finalized and construction crews being mobilized. For an idea of what construction looks like, Tilden Street, farther south, is the one intersection on the corridor marked under construction. There, DDOT is moving the Tilden Street bike lanes next to the curb at the intersection and adding green markings and buffers, at a cost of about five parking spaces on Tilden. When a crew reaches a Chevy Chase corner, DDOT says to watch for street detours and Emergency No Parking signs.
The Legation Street Signal Is the Closest to Switching On
The HAWK pedestrian signal at Connecticut Avenue and Legation Street is a separate project with its own notice, NOI 26-52-TSED, whose comment period closed April 17, 2026. The hardware is already up.
ANC 3/4G Commissioner Karrenthya Simmons posted an October 25 community update saying DDOT had finished the infrastructure, but Pepco still had to install electrical service before the signal could be turned on. Contract delays with Pepco moved the expected activation to the end of November, and she wrote that she hoped it would be working before the new year. If you walk this crossing over the holiday weekend, the signal may already be on or may still be waiting for power.
The Second Phase Is Where Traffic Patterns Shift
DDOT expects to build Phase 2 in 2027–2028. The biggest change on the Chevy Chase blocks is at Chevy Chase Parkway and Harrison Street. DDOT plans a full traffic signal there and will rebuild the southwest corner, closing Harrison Street to cars between Connecticut Avenue and Chevy Chase Parkway. A new crosswalk will cross Harrison at the Parkway, and the Harrison stop bar will move. This piece was added after the summer 2025 ANC meetings and first appeared in DDOT's December 2025 update.
Jocelyn Street is also scheduled for a full signal and a new south-leg crosswalk. Its bus stops will move so the northbound stop is on the north side of the intersection and the southbound stop is on the south side. At Nebraska Avenue, also in Phase 2, DDOT plans to rebuild the southwest corner to close the slip lane and move both bus stops to the far side of the intersection. It will also relocate the signal cabinet so it no longer blocks drivers' view.
All three of these intersections are listed as in procurement, meaning DDOT is still hiring a consultant team to take them through design and construction. ANC 3/4G's April 13, 2026 minutes record a DDOT presentation on the proposed changes between Oliver Street and Harrison Street, with no action taken.
Bus riders will see the same pattern at Military Road, Jocelyn Street and Nebraska Avenue: the stop moves across the intersection, and the off-peak parking shifts to make room. The rule has exceptions. Farther south, after reviewing comments on its notices, DDOT decided in September 2026 to keep the bus stops at Chesapeake Street and Brandywine Street where they are. Daylighting is still going ahead at Ellicott, Davenport, Chesapeake and Brandywine. DDOT added it in response to a joint resolution from ANC 3F and ANC 3/4G.
The Bike Lane Question Stays on the Calendar
DDOT's project page says the plans do not currently include a bike lane on Connecticut Avenue, and that the intersection work will not rule one out later. The agency is also preparing a Five-Year Strategic Bicycle Plan to update its bicycle priority network and set a construction work plan.
The debate that shaped the 2024 decision continues. On September 30, 2026, the Washington Area Bicyclist Association led a commute-hour ride from Chevy Chase Circle at 5720 Connecticut Avenue, leaving at 7:30 a.m. and finishing with a short rally at Dupont Circle. Ward 3 Bicycle Advocates, DC Bike Party and Potomac Pedalers co-sponsored it, and its stated message was aimed at DDOT and at the next mayor and Council. NBC4's coverage of the ride summarized both sides. WABA argued that protected lanes would serve local trips to school, shopping and the library. Save Connecticut Avenue argued that losing parking and curb access would hurt residents, disabled people, bus riders and businesses.
The Chevy Chase commercial blocks have been part of this debate from the start. When the bike lanes were dropped in 2024, Michael Harrison, manager of Parthenon Restaurant & Chevy Chase Lounge, told WTOP the decision was "a great victory for this community." The current plan for the Chevy Chase stretch is a set of corner and bus stop changes, on the same blocks traced in our history of the Hatcher Building and its Connecticut Avenue storefronts.
Keeping Track, Corner by Corner
Each intersection moves through procurement, design, pre-construction and construction separately, so DDOT's status table is the most reliable way to know when a crew will reach your corner. The table and the design drawings are posted on the Connecticut Avenue Multimodal Safety Improvements site, and comments go through DDOT's NOI portal. On the Chevy Chase blocks, the first-phase changes at Northampton Street and Military Road are both in pre-construction, and the Legation Street signal is waiting on Pepco's electrical service.
A moved bus stop, a closed block of Harrison Street or a new signal outside the door can change how a house works day to day. If you own or are considering a home near one of these Connecticut Avenue intersections and want to know how the planned changes affect that particular address, The Jill Schwartz Group can walk the block with you and talk it through. Request a private, confidential consultation.